INSTRUCTIONS FOR COMPLETING CAMPUS NAME DIVISION ONE (1)- GENERAL REQUIREMENTS

DATE

THE FOLLOWING ARE INTENDED TO BE THE SUGGESTED MINIMUM GUIDELINES FOR DIVISION ONE (1)- GENERAL REQUIREMENTS DOCUMENT. THE DESIGN PROFESSIONAL SHOULD THOROUGHLY DISCUSS EACH TOPIC WITH THE OWNER. IF ADDITIONAL INFORMATION IS NEEDED IN ORDER TO COMPLETE DIVISION 1, CONTACT: Contact Name, Contact Address, PHONE: PRIOR TO SUBMITTING THE ENTIRE DIVISION ONE FOR REVIEW.

AS A MINIMUM, THE DESIGN PROFESSIONAL SHOULD INCLUDE THE FOLLOWING TOPICS OR SIMILAR SECTIONS WITH APPROPRIATE LANGUAGE AS APPLICABLE:

Section 01010 Summary of The Work

01011 Contracts

01015 Contractor’s Use of Premises

01016 Occupancy

01018 Owner Furnished Items

Section 01020 Allowances

01021 Cash Allowances

Section 01025 Measurement and Payment

Section 01040 Coordination

01041 Project Coordination

01045 Cutting and Patching

Section 01050 Field Engineering

Section 01060 Regulatory Requirements

01062 Easements, Permits and Regulations

01063 Access to Work Site by Regulatory Authority

Section 01100 Special Project Procedures

01101 Physical Data

01103 Acceleration of the Work

Section 01200 Project Meetings

01210 Pre-construction Conferences

01220 Progress Meetings

Section 01300 Submittals

01310 Progress Schedules

01320 Progress Reports

01340 Shop Drawings, Product Data and Samples

01341 Roofers Qualifications

01370 Schedule of Values

Section 01400 Quality Controls

Section 01500 Construction Facilities and Temporary Controls

01510 Temporary Utilities

01520 Temporary Construction

01525 Construction Aids

01526 Trench Safety Systems

01530 Barriers and Enclosures

01540 Security

01550 Access Roads

01560 Temporary Controls

01580 Project Identification and Signs

01591 Field Offices and Sheds

Section 01600 Materials and Equipment

01610 Transportation and Handling

01620 Storage and Protection

01630 Project Options and Substitutions

Section 01700 Contract Closeout

01710 Final Cleaning

01711 Pre-final, Final Inspections and Occupancy

01720 Project Record Documents

01730 Operating and Maintenance Data

01740 Warranties and Bonds

01750 Spare Parts and Maintenance Materials

 

 

SPECIFIC REQUIREMENTS

Include the following in the indicated section or similar sections:

Section 01063 Access to Work Site by Regulatory Authority- shall contain the following statement:

" The contractor awarded this project agrees to allow any Federal or State inspector, acting in their official capacity, to have access to the job site"

Section 01015 Contractor’s Use of Premises- shall contain specific statements concerning contractor access, use of site, confining operations to project limits and use of existing facilities such as elevators and parking as appropriate.

Section 01016 Occupancy- Shall contain statements concerning Owner’s continued occupancy of existing and/or adjacent buildings where appropriate. Include statement that contractor is to provide minimum inconvenience to the Owner. Include statements about partial occupancy and/or moving equipment into the building prior to final completion and acceptance of the work, if appropriate.

Section 01018 Owner Furnished Items- Include statements concerning any owner furnished items for which the contractor has any responsibility for receiving, unloading, installing, making final utility connections, or otherwise coordinating with his work.

Section 01101 Physical Data- shall contain local National Weather Service Climatological Data for use in determining "unusually inclement weather" for the purposes of determining time extensions based on weather.

Section 01341 Roofers Qualifications- include the following statement:

"In addition to other submissions required by this section and Division 7, submit a photocopy of the manufacturer’s current and valid approved applications certificate."

Section 01510 Temporary Utilities- Include in this section statements concerning temporary electricity, lighting, heating, cooling, telephone, water, sanitary facilities, fire protection, etc. Discuss with Owner and include any of the utility items that the owner will provide for the contractor’s use on the project.

Section 01526 Trench Safety Systems- include specific language concerning requirements of 29 CFR 1926, Subpart P- Excavations, Trenching and Shoring of the Occupational Safety and Health Administration regulations for trench excavations which exceed five (5) feet. Include Approximate Angle of Repose Table P-1 and Trench Shoring Minimum Requirements Table P-2.

Section 01530 Barriers and Enclosures- Discuss with Owner the need for protective fencing on the project and include in this section. All sites where the Owner continues to use facilities and adjacent buildings will likely require temporary fencing.

Section 01540 Security- or similar section shall include statements concerning the protection of all landscape items, streets, drives, sidewalks, site features and adjacent property where appropriate. Include language concerning contractor’s responsibility for protection of all persons on site, including the general public through signs, guardrails, fencing, etc. Include statements concerning protection of existing work against weather. Include statement that the contractor is solely responsible for security and safety on site.

Section 01560 Temporary Controls- Include statements on construction cleaning, keeping site free from dust and debris. Include statements on erosion control, noise control, pest control, pollution control as appropriate.