INSTRUCTIONS FOR COMPLETING CAMPUS NAME DIVISION ONE (1)- GENERAL REQUIREMENTS
DATE
THE FOLLOWING ARE INTENDED TO BE THE SUGGESTED MINIMUM GUIDELINES FOR DIVISION ONE (1)- GENERAL REQUIREMENTS DOCUMENT. THE DESIGN PROFESSIONAL SHOULD THOROUGHLY DISCUSS EACH TOPIC WITH THE OWNER. IF ADDITIONAL INFORMATION IS NEEDED IN ORDER TO COMPLETE DIVISION 1, CONTACT: Contact Name, Contact Address, PHONE: PRIOR TO SUBMITTING THE ENTIRE DIVISION ONE FOR REVIEW.
AS A MINIMUM, THE DESIGN PROFESSIONAL SHOULD INCLUDE THE FOLLOWING TOPICS OR SIMILAR SECTIONS WITH APPROPRIATE LANGUAGE AS APPLICABLE:
Section 01010 Summary of The Work
01011 Contracts
01015 Contractor’s Use of Premises
01016 Occupancy
01018 Owner Furnished Items
Section 01020 Allowances
01021 Cash Allowances
Section 01025 Measurement and Payment
Section 01040 Coordination
01041 Project Coordination
01045 Cutting and Patching
Section 01050 Field Engineering
Section 01060 Regulatory Requirements
01062 Easements, Permits and Regulations
01063 Access to Work Site by Regulatory Authority
Section 01100 Special Project Procedures
01101 Physical Data
01103 Acceleration of the Work
Section 01200 Project Meetings
01210 Pre-construction Conferences
01220 Progress Meetings
Section 01300 Submittals
01310 Progress Schedules
01320 Progress Reports
01340 Shop Drawings, Product Data and Samples
01341 Roofers Qualifications
01370 Schedule of Values
Section 01400 Quality Controls
Section 01500 Construction Facilities and Temporary Controls
01510 Temporary Utilities
01520 Temporary Construction
01525 Construction Aids
01526 Trench Safety Systems
01530 Barriers and Enclosures
01540 Security
01550 Access Roads
01560 Temporary Controls
01580 Project Identification and Signs
01591 Field Offices and Sheds
Section 01600 Materials and Equipment
01610 Transportation and Handling
01620 Storage and Protection
01630 Project Options and Substitutions
Section 01700 Contract Closeout
01710 Final Cleaning
01711 Pre-final, Final Inspections and Occupancy
01720 Project Record Documents
01730 Operating and Maintenance Data
01740 Warranties and Bonds
01750 Spare Parts and Maintenance Materials
SPECIFIC REQUIREMENTS
Include the following in the indicated section or similar sections:
Section 01063 Access to Work Site by Regulatory Authority- shall contain the following statement:
" The contractor awarded this project agrees to allow any Federal or State inspector, acting in their official capacity, to have access to the job site"
Section 01015 Contractor’s Use of Premises- shall contain specific statements concerning contractor access, use of site, confining operations to project limits and use of existing facilities such as elevators and parking as appropriate.
Section 01016 Occupancy- Shall contain statements concerning Owner’s continued occupancy of existing and/or adjacent buildings where appropriate. Include statement that contractor is to provide minimum inconvenience to the Owner. Include statements about partial occupancy and/or moving equipment into the building prior to final completion and acceptance of the work, if appropriate.
Section 01018 Owner Furnished Items- Include statements concerning any owner furnished items for which the contractor has any responsibility for receiving, unloading, installing, making final utility connections, or otherwise coordinating with his work.
Section 01101 Physical Data- shall contain local National Weather Service Climatological Data for use in determining "unusually inclement weather" for the purposes of determining time extensions based on weather.
Section 01341 Roofers Qualifications- include the following statement:
"In addition to other submissions required by this section and Division 7, submit a photocopy of the manufacturer’s current and valid approved applications certificate."
Section 01510 Temporary Utilities- Include in this section statements concerning temporary electricity, lighting, heating, cooling, telephone, water, sanitary facilities, fire protection, etc. Discuss with Owner and include any of the utility items that the owner will provide for the contractor’s use on the project.
Section 01526 Trench Safety Systems- include specific language concerning requirements of 29 CFR 1926, Subpart P- Excavations, Trenching and Shoring of the Occupational Safety and Health Administration regulations for trench excavations which exceed five (5) feet. Include Approximate Angle of Repose Table P-1 and Trench Shoring Minimum Requirements Table P-2.
Section 01530 Barriers and Enclosures- Discuss with Owner the need for protective fencing on the project and include in this section. All sites where the Owner continues to use facilities and adjacent buildings will likely require temporary fencing.
Section 01540 Security- or similar section shall include statements concerning the protection of all landscape items, streets, drives, sidewalks, site features and adjacent property where appropriate. Include language concerning contractor’s responsibility for protection of all persons on site, including the general public through signs, guardrails, fencing, etc. Include statements concerning protection of existing work against weather. Include statement that the contractor is solely responsible for security and safety on site.
Section 01560 Temporary Controls- Include statements on construction cleaning, keeping site free from dust and debris. Include statements on erosion control, noise control, pest control, pollution control as appropriate.